Decision Maker: Assistant Director of Customers, Digital and ICT
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The current network firewall devices were
procured and implemented in 2006 and are end-of-life September
2018.
(1) To draw down £145,000 of the
£140,000 capital allocation identified in the capital
programme. The £145,000 allocation was identified for the
refresh of the current network firewalls and was approved as part
of the Capital Programme 2015/16 to 2018/19 at Full Council on
Tuesday 3rd March 2015. The allocation was spread over two
financial years, £72,000 in 2016/17 and £73,000 in
2017/18 but after discussions with finance ICT over £300,000
of capital allocations the capital programme finance approved
moving the full allocation of £145,000 to 2016/17; and
(2) To procure four Cisco Next Generation Firewalls and associated
equipment.
Option 1 - Do nothing: This would lead to the
Council failing the annual IT Health
Option 2 - Replace like for like: This option would meet
requirements of PSN Compliance but would deliver no added value and
would also incur a greater cost.
Option 3 - Replace with Next Generation Firewall Devices and Full
Security Suite: This option delivers the greatest level of threat
detection, prevention and remediation but is not achievable within
the current capital and revenue budgets.
Option 4 Recommended Option Replace with Next Generation Firewall
Devices: This option is achievable within existing capital and
revenue budgets.
Publication date: 28/02/2018
Date of decision: 17/03/2017