Decision Maker: Assistant Director of Communities
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Full details can be found within the attached
Officer Decision Record
1. To approved the allocation of
£326,688 Section 106 monies for the enhancement of Far
Field/Church Balk Open Space, Edenthorpe as follows:-
(a) £292,293 - Capital build estimated costs
(b) £34,395 - Revenue maintenance costs
Conditional on the developer accepting the Deed of Variation
outlined below.
2. To approve the award of tender and scheme implementation
conditional on the resulting project value being maintained within
the total available Section 106 funding (maximum £370,824)
unless other funding identified.
3. To approve the Deed of Variation to allow:
(a) the £300,000 (three hundred thousand pounds) payable
towards the provision enhancement and maintenance for 15 years to
include the Public Open Space at the Church Balk Fields/Far Field
site within the parish of Kirk Sandall and the Mere Lane site
within the parish of Edenthorpe
(b) for part of the Section 106 sum to be set aside for the
maintenance for a period of 15 years of the Public Open Space at
the Church Balk/Far Fields site and the Mere Lane site.
Deed of Variation - There are no other
suitable alternative options considered available. To enter into a
Deed of Variation is the most appropriate course of action to take
with regards to this project
Overall Scheme - There are no other suitable alternative options
considered available. The proposed approach is considered the most
appropriate and realistic route to follow to ensure the proposed
enhancements are delivered.
Publication date: 09/03/2018
Date of decision: 22/06/2017
Accompanying Documents: