Decision Maker: Assistant Director of Finance & Chief Financial Officer
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Doncaster Council has submitted a bid to
deliver a new special school (Bader School - SEN Free School) on
vacant land behind Hungerhill School.
At Cabinet on 18 July, 2017, authority was delegated to the
DIrector of People and Chief Financial Officer in consultation with
Portfolio Holder Children Young People and Schools to negotiate
with the Education and Skills Funding Agency (Now the Department
for Education) to deliver the building of the school as well as the
effective set up of an effective school delivery model in
conjunction with the agreed provider.
Agree to release the capital budget for the
delivery of the Bader School (SEN Free School) to enter into
contract with Willmott Dixon in two stages with delegated Authority
for spend to the Director of People and the Chief Financial Officer
in consultation with the Mayor:-
Stage 1 - For the construction of new road and associated services
to the red line boundary;
Stage 2 - For the construction and delivery of the school within
the red line boundary following receipt of Capital Approval from
the Department of Education.
The Council and its Partners were instrumental
in the initial design work carried out to determine a budget figure
which was approved within the Heads of Terms. The delivery through
the SCAPE Framework has allowed early engagement with the
contractor and is OJEU compliant.
Alternative delivery options could remove the Council's direct
input into the design work and could result in an increase to the
budget which would require renegotiation with the Department for
Education and would further extend the delivery of the school. This
was not recommended.
Publication date: 13/06/2019
Date of decision: 08/03/2019