In January 2018 the Working Assurance Board
considered a 'DGT Inclusive Growth Resource Request' for the
following:-
2018/19 - £707, 830
2019/20 - £743, 660
2020/21 - £763, 657
Total - £2, 215, 147
The Programme Board approved the initial transformational projects
and actions to deliver Inclusive Growth and financial allocations
of £360,000 per annum permanent increase to the core revenue
budget and £347, 830 for 2018/19 from temporary available
budget were approved by Assurance Board, chaired by the Chief
Financial Officer.
Funding was also earmarked for 2019/20 and 2020/21 subject to the
outcome of a review of impact at the end of 2018/19.
The information contained within the report aimed to provide
details of progress made across all areas as a result of the
additional funding in 2018/19 and sought to confirm the drawdown of
STF for 2019/20 and 2020/21.
To approve the draw down of £394, 510 of
earmarked Service Transformation Funds (STF) in 2019/20 and
£382,670 in 2020/21 to contribute to the delivery of
Doncaster Growing Together programme activities.
To note progress made in delivery of previously approved activities
in 2018/19.
Option 1 - Do Nothing - Failure to secure
Service Transformation Funds would result in activities ceasing
delivery. These activities are high profile and there is therefore
reputational risk with this course of action.
Option 2 - Submit reduced request for funds - A full review of
requested financial allocations has been conducted and adjustments
have already been included where these are considered appropriate.
Further reductions would be detrimental to the success of the
programme.