Decision Maker: Director of Learning, Opportunities and Skills
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Doncaster Council are self-delivering the new
SEN school on vacant land behind Hungerhill School, with funding
from DfE, following a successful free school bid.
The DfE will make funds available for drawdown to deliver the
project following the granting of planning permission. The
aspirational opening date of the school is 1 September 2020, which
requires work to begin as soon as possible should planning
permission be granted at the Extraordinary Planning Committee
meeting scheduled for 30 July 2019
Following the receipt of the project funds from the DfE, the
£200,000 will be reallocated back to the Basic Needs
Allocation.
To make a payment to Wilmott Dixon
Construction of up to £200,000 for site set up costs in
August 2019 for the delivery of the 'Bader School' (SEN Free
School) - a new 100 place Communication and Interaction (C&I)
Special School with an age range of 5-19. This will be achieved by
a variation to the existing pre-construction services agreement
PCSA with the agreement of Wilmott Dixon.
To not make payment to Wilmott Dixon and run
the risk that the project delivery date will slip, resulting in the
school not opening on 1 September 2020.
Publication date: 25/09/2019
Date of decision: 01/08/2019
Accompanying Documents: