Decision Maker: Service Director Place
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
A per the ODR
Place/Planning/09/00190/OUTA/02_2024 has already allocated funding
for a pedestrian crossing on West End Lane, Rossington the cost of
delivering this would be in the region of £ . This would
improve the safety of road using within the area.
1. To approve the allocation of £ of
S106 Monies for Pedestrian Crossing – West End Lane,
Rossington
2. To gain S151 Officer approval to add the scheme to the
Council’s Capital Programme.
3. To give delegated authority to the Director of Place to
implement and deliver the scheme.
To not utilise the s106 monies that have
already been paid to the Council. As the named project no longer
requires funding to deliver (given an alternative route was
implemented), the funds would not be utilised for the named project
and would be returned to the developer despite the developer having
agreed to allow these monies to be spent elsewhere in the locality
on this worthwhile project – REJECTED.
Publication date: 29/08/2024
Date of decision: 15/07/2024
Accompanying Documents: