In the 2023-24 Quarter 4 Finance and
Performance Improvement Report that was presented to the Mayor and
members of cabinet on 19th June 2024 it referred to an underspend
of £3.1m on the general fund which enables the Council to
allocate resources to provide targeted funding towards priorities,
which have been identified by our residents. In addition, a further
£0.2m is available following a review of earmarked
reserves.
One of these priorities is £800,000 targeted towards road
resurfacing, this funding is in addition to the 2023/24 and 2024/25
Network North Roads Re-surfacing Fund of £1.6m for the 2
years, matching the
annual allocation with CDC funding. This funding will be allocated
on the same basis as the Network North Roads Re-surfacing Fund and
approved in the quarterly Finance & Performance
Improvement
report.
This was fully approved at cabinet on 19th June 2024.
Approval of:
• The draw down 2023/24Underspend Ear Marked Reserve.
• Allocation of £800k Ear Marked Reserve for Highways
Maintenance, to be used on the maintenance of local roads within
the City of Doncaster which consist of:
o Identify individual sites for carriageway permanent
patching.
o Resurfacing of local / urban estate roads, identified on a worst
first basis
o Robust & permanent carriageway patching.
• Approval to add new schemes to the Capital Programme for
2024/25.
Not to accept the £800k ear marked
reserve for highway maintenance would not be viable as the service
area is already underfunded and requires an influx of over
£150m to remove the existing non-funded build-up of
maintenance works to carriageways.
In view of the existing non-funded works situation this option has
been rejected.