Decision Maker: Assistant Director of Trading Services and Assets
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The items of plant have been identified as
required immediately, prior and outside the current Fleet
Replacement Programme which is being prepared for Cabinet. The
replacement of these large plant items is critical to front line
delivery, and they have now exceeded their life expectancy, and are
proving unreliable and uneconomic to repair.
User sections have/will have to hire in machines to cover critical
services of replacements are not purchased. Hiring in is not cost
effective to the authority.
To procure x 3 items of plant with funding
from IMF
x 1 loading shovel - Gritting Operations approx
£110,000
x 1 Telescopic handler - Stores/Gritting Operations approx
£52,000
x 1 Mini Excavator - Cemeteries approx £30,000 (stolen)
Total Spend Circa £192,000
Option 1 - Order the plant now to support
effective delivery of front line critical services and statutory
obligations. (Recommended)
Option 2 - Do nothing - although the timely delivery of these items
lie on the critical path of the service and associated savings and
service improvements may be jeopardised if delivery is
forestalled
Option 3 - Hire in equipment to cover the period to the
implementation of the Fleet Replacement Program and incur the
associated costs to budget.
Publication date: 06/12/2018
Date of decision: 15/11/2018